Walker Advanced Manufacturing Innovation Centre: WC

The 15,000 square-foot Walker Advanced Manufacturing Centre will significantly enhance Niagara College’s capacity for applied research projects. The ground floor will feature specialized labs with 3D printers, scanners, and other equipment along with office space for student and staff scientists and researchers. The top floor will house Niagara College Research and Innovation offices and space for ncTakeOff – the college’s entrepreneurship hub. Research and Innovation’s digital media and web solutions group will also be on the second floor along with meeting and conference space.

The Centre is named in recognition of a $1.2 million contribution from Niagara’s Walker family and its company, Walker Industries Holdings Limited. The contribution is the largest corporate donation in Niagara College history.

Work began on the facility in May, 2015 and completion is scheduled for spring 2016.

Timelapse Video of Construction

Canadian Food and Wine Institute Expansion: NOTL

Rendering of the expansion at the Canadian Food and Wine Institute

The expansion of the Canadian Food and Wine Institute at the Niagara-on-the-Lake Campus supports Niagara College’s position as Canada’s premier college for food and fermentation sciences and will help meet growing demand for its culinary, wine and brewery programs. The 13,000 square-foot one-floor addition will be constructed on the east side of the existing CFWI building and will include an expanded baking and pastry lab, quantitative lab, qualitative lab and central stores. Renovations to the existing stores area will complete a culinary, butchery and charcuterie lab. Construction began in October, 2015 and completion is scheduled for January, 2017.


  • Academic Training: WC

    Currently in the design phase, this 10,300 square-foot addition to the north side of the Athletic Centre will provide a new academic lab with longer-term flexibility as a second gymnasium.

  • Cafeteria and Justice Studies (Simcoe Extension): WC

    Currently in the design phase, this 37,000 square-foot expansion to the north-end of the Simcoe Building will include a student activity centre, 600-seat cafeteria (including Tim Hortons and several other outlets like Subway), kitchen and servery. The project will also include an expansion of the existing prayer room. Two-storey renovations to the north end of the Simcoe Building will accommodate justice studies programs, demonstration labs and four classrooms proposed. Construction projection: May 2016 – August 2017.
  • Fitness Centre/Classrooms: NOTL

    Currently in the design phase, this 20,000 square-foot expansion allows for a possible future expansion of an additional two floors. The project includes an expansion to the east side of the campus replacing the existing facility, with an upgraded, larger fitness centre with change rooms, an exercise studio, offices, reception and six new 40-seat classrooms. Construction projection: May 2016 – October 2017.

  • Student Services Renovations/Learning Commons and Cafeteria: NOTL

    Currently in the early design phase, this project will include renovations to existing areas, including student services on the ground level and the student commons (cafeteria) and learning commons areas. Construction will be completed in 3 phases:

    • Phase 1: Ground Level – Administration, Health & Wellness, Recruitment, Washrooms (M+F), Relocate Test Center (Ground Floor), Student Services (Cafeteria), and Gym. Projected construction dates: May 2016 – August 15, 2016
    • Phase 2: Academic Services, 1st Floor Learning Commons & Washroom expansion (M+F). Projected construction dates: July/August 2017
    • Phase 3: Lower Level Fitness, Student Services. Projected construction dates: January 2018 – May 2018
  • Student Services Renovations/Student Commons: WC

    Currently in the program development phase, this project will include renovations to accommodate integrated student services, upgrades to the library including a student test centre and the creation of a student commons. Construction will be completed in 3 phases:

    • Phase 1: AHI Counselling. Projected construction dates: May 2016 – September 2016
    • Phase 2: Administration, Health & Wellness , CSEL, COOP, Student Services Renovations. Projected construction dates: January 2017 – September 2017
    • Phase 3: Library/Learning (Former Cafeteria). Projected construction dates: October 2017 – February 2018
  • Infrastructure/Mechanical projects

    Roads and parking lots: Niagara-on-the-Lake Campus – timing TBD

    Hydro and generator upgrades: Niagara-on-the-Lake Campus – May, 2016-December, 2016

    Infrastructure updates: Welland Campus – timing TBD